Welcome to California California Home
Welcome to California - images of Golden Gate Bridge, ocean sunset, waterfall, flowers, city skyline
CTC Home Page
Programs
Board
Library/Data Downloads
Current Information
Job/Exam Opportunities
Propositions 40 and 50
Project Information
Contracts and Concessions
CTC image
Progress Report
July 1997
Introduction
Tahoe - A Treasure and Challenge
The Role of the California Tahoe Conservancy
Project Planning and Coordination
Environmentally Sensitive Land
Erosion Control
Stream Environment Zone
Cold Creek Restoration Project
Land Coverage and Other Marketable Rights
Public Access and Recreation
Kings Beach Public Lakefront Access
Wildlife Enhancement
Management
Interpretation
The Future
Summary of Projects
Lake Tahoe License Plate
California Tahoe Conservancy

   My CA
 Progress Report

Cold Creek Restoration Project

The Cold Creek restoration project in South Lake Tahoe is one of the largest SEZ projects so far undertaken by the Conservancy, with a total project cost of $1,400,000.

The project, completed in 1994, re-created more than a mile of meandering stream channel, and reconverted a defunct man-made lake into a half mile long meadow that now absorbs runoff and provides habitat for fish and wildlife.

Cold Creek is particularly important because it is a major tributary to Trout Creek, the second largest tributary to Lake Tahoe. Cold Creek drains 13 square miles of the 37 square mile Trout Creek watershed.

Some 40 years ago, the creek was rerouted into a ditch, and a dam and lake were created in the meadow, with the hope of enhancing an adjacent subdivision. The effort was not successful, and concerns about dam safety, flooding, erosion, and nuisance odor from decaying algae prompted the City of South Lake Tahoe to apply to the Conservancy for a restoration grant.

Construction began in August 1994. The old "Lake Christopher" dam across the meadow was removed and the man-made channel was filled in.

The area was then reshaped to a more natural condition and revegetated. The new creek channel was constructed for re-create natural stream conditions. Natural materials, including tree root wads and willow and sod transplants were used to stabilize the stream banks.

Since construction, this project has experienced two successive wet winters and the newly restored creek not only sustained the flows without significant damage, but allowed the water it was carrying to flood over into the meadow, as it was designed to do, and this has restored the health of the meadow vegetation.

In addition, hundreds of tons of sediment have been deposited in the meadow, instead of being carried into Lake Tahoe.


Back to Top of Page

California Tahoe Conservancy
1061 Third Street· South Lake Tahoe, CA 96150 · (530) 542-5580 · (530) 542-5591 (fax)
© 2003 State of California. Arnold Schwarzenegger, Governor.
Conditions of Use Privacy Policy CTC Disclaimer